Here are the major construction project priorities for the coming week:

  • Continue framing along western part of sanctuary that includes the narthex, confessional, vesting room, devotional prayer space and baptistry
  • Final preparation for concrete pour of baptismal font
  • Prayer garden planning
  • Work with architects on kitchen procurement plan
  • Final irrigation plan in place
  • Electrical review of outlets
  • Status check with artist on the stain glass window at baptistry

Any questions on these items or in general – please contact our Project Manager, David Mastroieni at 503-998-1070 or ddmconsulting@msn.com

Thank you!!

Change Lives. Give Hope.

Are you working for your Kingdom or for God's Kingdom? We ask for your support as we work in the name of God, our Loving Father, to Strengthen our community as we Serve and Share with the blessed and humble people of our community. To succeed, we will depend on the full participation of our Parish and support from other faithful as well. Please thoughtfully pray about the how you can support the goodness of God in your life and in the lives of others, by contributing to our Building Campaign

Love the Lord with all your passion, and prayer, and intelligence, and energy. Mark 12:30