Here are the major construction project priorities for the coming week:

  • Framing continues
  • Sitework for south parking area
  • Mechanical sub-contractor continues with their scope
  • Site walk with architect for power plug-ins
  • Trash enclosure layout
  • Floor grinding continues in the church
  • Start work on water line from SE 148th Ave. into the Church
  • Final kitchen equipment negotiation
  • Coordinate final pew measurements with New Holland

Any questions on these items or in general – please contact our Project Manager, David Mastroieni at 503-998-1070 or ddmconsulting@msn.com

Change Lives. Give Hope.

Are you working for your Kingdom or for God's Kingdom? We ask for your support as we work in the name of God, our Loving Father, to Strengthen our community as we Serve and Share with the blessed and humble people of our community. To succeed, we will depend on the full participation of our Parish and support from other faithful as well. Please thoughtfully pray about the how you can support the goodness of God in your life and in the lives of others, by contributing to our Building Campaign