Published November 02, 2017

Design and Construction Update

Week of October 30 – November 3, 2017

Here are the major construction project priorities for the coming week

  • Mechanical/electrical installation continues
  • Cedar siding continues 
  • Complete insulation – interior
  • Complete sidewalk crossing through parking area
  • Complete sidewalk near Serendipity
  • Set sheetrock schedule
  • Set painting interior ceiling schedule in church
  • Overall scheduling meeting with the GC and sub-contractors
  • Coordinate final delivery date and installation with New Holland Manufacturing regarding pews
  • Continue working with City of Portland regarding water meter location and water line


Change Lives. Give Hope.

Are you working for your Kingdom or for God's Kingdom? We ask for your support as we work in the name of God, our Loving Father, to Strengthen our community as we Serve and Share with the blessed and humble people of our community. To succeed, we will depend on the full participation of our Parish and support from other faithful as well. Please thoughtfully pray about the how you can support the goodness of God in your life and in the lives of others, by contributing to our Building Campaign

Love the Lord with all your passion, and prayer, and intelligence, and energy. Mark 12:30