Published November 02, 2017

Design and Construction Update

Week of November 6 – November 10, 2017

Here are the major construction project priorities for the coming week

  • Mechanical/electrical installation continues
  • Siding continues; complete east side and north side of church 
  • Window installation continues
  • Continue working with City of Portland regarding water meter location and water line
  • Work with City of Portland on final street improvement plan
  • Grading of the parking lot expansion areas (southeast side of the property and west side near north entrance
  • Asphalt paving Friday, November 10
  • Painting of ceiling in church


Change Lives. Give Hope.

Are you working for your Kingdom or for God's Kingdom? We ask for your support as we work in the name of God, our Loving Father, to Strengthen our community as we Serve and Share with the blessed and humble people of our community. To succeed, we will depend on the full participation of our Parish and support from other faithful as well. Please thoughtfully pray about the how you can support the goodness of God in your life and in the lives of others, by contributing to our Building Campaign