Published November 10, 2017

Design and Construction Updates

Week of November 13 – November 17, 2017

Here are the major construction project priorities for the coming week

  • Mechanical/electrical installation continues
  • Siding continues; west side of church 
  • Final window installation
  • Meet with City of Portland regarding water meter location and water line
  • Work with City of Portland on final street improvement plan
  • Sheetrock interior of church
  • Interior painting continues

Any questions on these items or in general – please contact our Project Manager, David Mastroieni at 503-998-1070 or ddmconsulting@msn.com

Change Lives. Give Hope.

Are you working for your Kingdom or for God's Kingdom? We ask for your support as we work in the name of God, our Loving Father, to Strengthen our community as we Serve and Share with the blessed and humble people of our community. To succeed, we will depend on the full participation of our Parish and support from other faithful as well. Please thoughtfully pray about the how you can support the goodness of God in your life and in the lives of others, by contributing to our Building Campaign

Love the Lord with all your passion, and prayer, and intelligence, and energy. Mark 12:30